BI Toolkit
BI Toolkit
ReachBack
With regard to procurement legislation, is there a need for suppliers to be debriefed in writing?
Procurement
CIPS_Expert
22 February 2013 13:12
2
No, there is no such requirement, the format can be decided by the utility in question.
Related topics
Topic
Replies
Views
Activity
With regard to procurement legislation, is debriefing required for part B contracts?
Procurement
1
382
22 February 2013
With regard to procurement, what requirements with regard to debriefing exist since the 20/12/2009 regulations were instigated?
Procurement
1
426
22 February 2013
With regard to procurement legislation, at what stage must utilities reveal award criteria to tenderers?
Procurement
1
352
22 February 2013
With regard to procurement legislation, is a utility entitled to consider firms for tender whom have not responded to the Official Journal notice?
Procurement
1
411
22 February 2013
With regards to public procurement, what is the procedure if an individual does not award a contract?
Procurement
1
351
22 February 2013