Retention is held in trust to ensure that the contractor will receive payment if the employer is liquidated.
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
Under JCT Standard Building Contract 2009, a contract was terminated due to insolvency on behalf of the contractor. Can a liquidator insist that the full payment of the balance plus retention is immediately due? | 1 | 731 | 6 February 2013 | |
Is Retention held on all Loss & Expense; cl 4.14.2.3 JCT SBC 2016 | 1 | 232 | 21 June 2024 | |
In construction contracts, what are 'performance bonds'? | 1 | 460 | 4 February 2013 | |
JCT retention release but more work keeps on being instructed | 2 | 362 | 23 November 2023 | |
In a construction contract, if an employer is unable to award possession by the due date can this be overcome by the architect instructing for the Works to be postponed? | 1 | 598 | 4 February 2013 |