What is the purpose of Option X17 low performance damages?

What is the purpose of Option X17 low performance damages?

1 Like

Where the performance of the works in use fails to reach a specified level due to a design or other fault of the Contractor and the Defect is not corrected so that it is listed in the Defects Certificate, the Employer should be able to recover the damages he suffers in consequence. This Option provides for these damages to be recovered as liquidated damages.