What is the procedure if the Contractor’s quotation for reduced Prices or an earlier Completion Date is not accepted?

What is the procedure if the Contractor’s quotation for reduced Prices or an earlier Completion Date is not accepted?

1 Like

A Contractor may submit a quotation for reduced Prices or an earlier Completion Date in order to accept a Defect. If this quotation is not accepted by the Project Manager, there is no further action.