The Employer has terminated because the Project Manager has given an instruction to stop/not start work due to reasons other than the Contractor’s or the Employer’s default and has not given an instruction to re-start within three weeks (R20). What is the amount due?
1 Like
The amount due will be that outlined in A1 (Clause 93.1) and A2 (Clause 93.2) . A1 includes:
an amount due for normal payments,
the Defined Cost for Plant and Materials
Other Defined Cost expected to be incurred in completing the whole of the works,
amounts retained by the Employer,
deduction of un-repaid balance of an advanced payment.
A2 includes: The forecast Defined Cost of removing Equipment.