BI Toolkit
BI Toolkit
ReachBack
Once a local authority has approved a building plan, is there a time limit for the approved work?
Planning and Architecture
Part A Structure
Build_Regs_Advisors
6 February 2013 14:58
2
Yes, work must commence within three years of the time that the plan is approved.
Related topics
Topic
Replies
Views
Activity
When is it permissible for building work to begin when an application has been submitted to a local authority?
Part A Structure
1
428
7 February 2013
When does work need to start after planning permission is granted?
Application Process
1
495
25 January 2013
When is it permissible for building work to begin when an application has been submitted to an approved inspector?
Part A Structure
1
394
7 February 2013
When does work need to start after planning permission is granted?
Planning Permission
1
487
25 January 2013
With regards to Building Regulations, how long are approved plans valid for?
General
1
357
7 February 2013