ReachBack
Once a local authority has approved a building plan, is there a time limit for the approved work?
Planning and Architecture
Part A Structure
Build_Regs_Advisors
6 February 2013 14:58
2
Yes, work must commence within three years of the time that the plan is approved.
Related topics
Topic
Replies
Views
Activity
When is it permissible for building work to begin when an application has been submitted to a local authority?
Part A Structure
1
414
7 February 2013
With regards to Building Regulations, how long are approved plans valid for?
General
1
353
7 February 2013
When a full plans application is submitted to a local authority, how long do they have to approve or reject the plan?
General
1
381
7 February 2013
When is it permissible for building work to begin when an application has been submitted to an approved inspector?
Part A Structure
1
390
7 February 2013
How long is planning permission valid for once it has been authorised by the local authority?
General
1
419
7 February 2013