NEC3 ECC TRA in Programme is Contractor's risk- what is the completion date when reviewing the programme?

Hi, you need to be careful here because there are 2 different matters. 1 Is planned Completion, the date by which the Contractor forecasts it will achieve Completion. This should include TRA because the Contractor carries the risk. 2 is the completion date that is the date by which the Contractor is required to have achieved Completion and if it fails to do so will/may be exposed to damages. Accepting the clause 32 programme does not alter the completion date, also if the Contractor is showing planned Completion past the completion date acceptance does not delete damages. Acceptance of the programme is acceptance that the plans are realistic. hope that helps