On a ECC (3) option C contract if the Project Manager ask the Contractor to submit a quotation for a proposed instruction and after he receives the quotation decides not to go ahead with the work can the contractor put in a notification of a compensation event to pay for the staff time in producing the quotation should the Project manager agree and raise the target cost for the amount of the NCE?