BI Toolkit
BI Toolkit
ReachBack
NEC ECC: What is the dividing date, as it does not seem to be a defined term
NEC3 and NEC4 Contracts
Compensation Events
Neil_Earnshaw
24 February 2020 14:11
3
Please can you clarify which NEC contract you are referring to? NEC3 or NEC4 ECC?
Forecast costs in a CE - Forecast from when?
show post in topic
Related topics
Topic
Replies
Views
Activity
NEC ECC: Dividing Date in NEC4
Compensation Events
1
944
7 January 2020
NEC ECC: In step 3 (of assocaited question), where is progress taken up to; to the CE notification date?
Time
3
1171
22 April 2020
NEC ECC: Dividing date in NEC4
Compensation Events
1
516
8 January 2020
NEC4 ECC Time of Event definition
NEC3 and NEC4 Contracts
1
391
29 September 2020
NEC Defined Cost / dividing date
NEC3 and NEC4 Contracts
1
947
9 November 2020