How is PWDD calculated when it is not just completed activities but also partially completed activities as the sum for the total of the Prices each month?
1 Like
Don’t know why an Employer would add in the words “partially” in that clause as a Z clause. The whole idea is it is a clear measure - only completed items are paid for, which is why the Contractor should break down their activity schedule to a reasonable level of detail.
You ask what it means when you add those words - the answer is subjectivity, so the advise is don’t!