Although this scenario can and has arisen, in legal terms the clerk of works has no such power. If a clerk of works attempts to stop the Works then (s)he is considerably exceeding his / her actual powers. Should a contractor cease work based on such an instruction, they would be in breach of contract.
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
What are the legal ramifications if a clerk of works approves defective work? | 1 | 843 | 5 February 2013 | |
If an architect under-certifies, can the contractor suspend work under the Construction Act? | 1 | 409 | 5 February 2013 | |
In the event that work is omitted, is a contractor entitled to loss of profit? | 1 | 1334 | 5 February 2013 | |
If a contractor runs over time and an architect over-certifies, will there be any legal issues should the employer desire to terminate the contract? | 1 | 547 | 6 February 2013 | |
Should an architect find no-one in charge on a site, can a project be halted until such time as there is someone on site with this responsibility? | 1 | 664 | 5 February 2013 |