ReachBack
If a liquidated damages claim exists, must there by implication also be clause in the same amount for early completion?
JCT Contracts
JCT_Experts
5 February 2013 15:51
2
No. There can be a bonus clause, but it is totally unrelated to liquidated damages.
Related topics
Topic
Replies
Views
Activity
Can a sub-contract incorporate liquidated damages?
JCT Contracts
1
420
5 February 2013
If an employer terminates a contract in its late stages, is it legally permissible for an employer to subtract liquidated damages from the original contractor until the contract has been completed by other contractors?
JCT Contracts
1
442
5 February 2013
If an employer suffers no loss, is it still legally permissible to deduct liquidated damages?
JCT Contracts
1
534
5 February 2013
JCT: If a completion date on a JCT with quants is not stated but an amount of weeks to complete the work is stated can this affect the liquidated damages?
JCT Contracts
1
396
9 October 2017
Why do contractors state occasionally that employers are not permitted to deduct penalties?
JCT Contracts
1
473
5 February 2013