How is the Contractor paid for management of: the Contractor’s design; provision of Site services; and construction and installation of the works?

How is the Contractor paid for management of: the Contractor’s design; provision of Site services; and construction and installation of the works?

Management of: the Contractor’s design; provision of Site services; and construction and installation of the works is covered by the Fee (see Clause 20.2).