How can KPIs be used in multi-party arrangements?
Where the Employer wishes to offer incentives to members of the project team, Option X12 (Partnering) should be used. The Incentive sharing arrangements in Option X12 are flexible enough to cover the payment of different incentives to different Partners, so Option X20 is unnecessary when Option X12 is used.