Do the weather measurements have to be recorded on Site?

Do the weather measurements have to be recorded on Site?

The data routinely recorded at a weather station close to the Site could be used as an alternative to recording on the Site. If there is not a weather station nearby, the weather measurements should be made using gauges and equipment installed at the place stated in the Contract Data.