Scenario
A Subcontractor is on site who has a works which have a Key Date for a condition to met. The Subcontractor through his own delays was due to miss the Key Date by several weeks. Some time after he missed the Key Date and while he was still working on these works, he was given a CE to provide works which took a week to complete and it was the last 3 days of this week which was the driver for his works to meet the condition of the Key Date (he would have finished his works only 3 days prior if it wasn’t for the CE to be issued).
Question
- What is his entitlement to time passed the Key Date? Is it only 3 days or it is the full duration from commencement to completion?