NEC ECC: Option E Defects cost
|
|
1
|
1068
|
28 April 2020
|
NEC ECC: Employers Design incorrect - is this a Defect?
|
|
1
|
655
|
10 April 2020
|
NEC ECS - Different options for correcting a Subcontractor defect
|
|
1
|
518
|
7 April 2020
|
NEC ECC: How is the assessment formed when accepting a defect under Option A?
|
|
2
|
1774
|
30 March 2020
|
NEC ECC: Temporary propping of bracing - is this a Defect?
|
|
1
|
638
|
13 March 2020
|
NEC ECSC: ownership and title to construction work
|
|
1
|
623
|
2 March 2020
|
NEC ECC: Supervisor recording defects
|
|
2
|
646
|
27 February 2020
|
NEC ECC: Temporary Work Design and Clause 23.1
|
|
1
|
800
|
21 February 2020
|
NEC ECC: Can Contractor claim cost if delayed in correcting a defect that they caused?
|
|
3
|
688
|
6 February 2020
|
NEC ECC: Defects and Contractor warranties
|
|
1
|
1338
|
5 February 2020
|
NEC ECC: Option C - Contractors Denies a Notified Defect is a Defect
|
|
4
|
691
|
20 January 2020
|
NEC ECC: Supervisor missed a defect, what is their liability?
|
|
3
|
981
|
6 December 2019
|
NEC ECC: Defective works
|
|
1
|
604
|
21 November 2019
|
NEC ECC: Cost of Correcting Defect
|
|
3
|
641
|
6 November 2019
|
NEC ECC: Defects, Burden of Proof
|
|
1
|
808
|
4 November 2019
|
NEC ECC: Timing for acceptance of defects 44.1
|
|
1
|
549
|
29 October 2019
|
NEC ECC: Under an Option A contract how are the Employers Costs of correcting a Defect after Completion recouped if there is no retention available?
|
|
2
|
840
|
26 October 2019
|
NEC ECC: Defiinition of 'breach' or 'non performance'
|
|
1
|
576
|
17 October 2019
|
NEC ECS: Quotation for acceptance of Defect
|
|
4
|
910
|
14 October 2019
|
NEC ECC: Contractor poor performance
|
|
1
|
1444
|
13 October 2019
|
NEC ECC; Management of latent Defects?
|
|
1
|
1218
|
18 September 2019
|
NEC ECC: Accepting the correction of a Defect
|
|
1
|
998
|
13 September 2019
|
NEC ECS: Correcting a defect we know the end Client has accepted
|
|
1
|
466
|
13 September 2019
|
NEC ECC: Dual Defects Found from two different Contractors
|
|
1
|
541
|
4 September 2019
|
NEC ECC: Defect not spotted immediately
|
|
1
|
500
|
30 August 2019
|
NEC ECC: Clause 45.2 - non access to correct defect
|
|
1
|
998
|
29 August 2019
|
NEC ECC: Should the Supervisor notify the PM prior to any search of Defects?
|
|
1
|
779
|
6 August 2019
|
NEC ECC: Option A - Zero Defects
|
|
3
|
1435
|
12 July 2019
|
NEC ECC: Failed welds - whose liability?
|
|
1
|
528
|
9 July 2019
|
NEC ECC: Appointing others to correct uncorrected Defects
|
|
1
|
532
|
1 July 2019
|