NEC ECC: Clause 32.2 submitting programme on PM instruction

No PMI is a compensation event unless there is a reason to notify it as one under clause 60.1. Several instructions will never give rise to a compensation event. Clause 32.2 allows the PM to instruct a revised programme. Is this really that unreasonable? I always say a Contractor should be updating their programme as a minimum weekly so the fact they are asking for one every two weeks is not at all unreasonable and something you should be doing anyway and be able to share with them.

Frankly you should probably thank the PM for making you do something you should be doing anyway!!