How should I dispose of asbestos waste?
Asbestos waste describes any asbestos products or materials that are ready to be disposed. This includes any contaminated building materials, dust, rubble, used tools that cannot be decontaminated, disposable PPE (personal protective equipment) and damp rags that have been used for cleaning. Asbestos waste must be placed in suitable packaging to prevent any fibres being released. This should be double wrapped and appropriately labelled. Standard practice is to use a red inner bag – marked up with asbestos warning labels – and a clear outer bag with appropriate hazard markings. Intact asbestos cement sheets and textured coatings that are firmly attached to a board should not be broken up into smaller pieces. These should instead be carefully double wrapped in suitable polythene sheeting (1000 gauge) and labelled.
Asbestos waste should only be handled by a licensed disposal site. Your [ How to deal with fly-tipped asbestos waste ](http://www.hse.gov.uk/pubns/guidance/a38.pdf).