|
NEC 3 Option B - Reduced Quants Extended Programme
|
|
1
|
488
|
19 October 2023
|
|
Late Submission of Programme Resulting in Losses
|
|
1
|
626
|
19 October 2023
|
|
NEC3 contract - single Defects notice with Schedule of Defects attached
|
|
1
|
386
|
18 October 2023
|
|
Is there a switch date in NEC 3?
|
|
1
|
483
|
18 October 2023
|
|
Clause 63 - Assessment of CE's on NEC3 TSSC's & Switch Date
|
|
1
|
236
|
11 October 2023
|
|
Delays Resulting To Increased Cost But X1 IS Not Included
|
|
2
|
334
|
10 October 2023
|
|
NEC3 ECC Option A - Clause 60.1 (2) or 60.1 (4)
|
|
1
|
611
|
4 October 2023
|
|
Withdrawal of a subcontractor and Clause 60.1(19)
|
|
2
|
331
|
26 September 2023
|
|
NEC4 Option A Third Party Design Review
|
|
1
|
287
|
21 September 2023
|
|
NEC4 ECSS Defined Cost and Fee
|
|
3
|
567
|
19 September 2023
|
|
Contractor remedy missing
|
|
4
|
405
|
15 September 2023
|
|
NEC3 Option B - Can a Contractor decline to carry out a Compensation Event
|
|
2
|
759
|
25 August 2023
|
|
Issuing drawings Compensation Event or PMI (or both!)
|
|
5
|
630
|
25 August 2023
|
|
Assessing Prolongation on CE's and Cl.62 Programmes
|
|
3
|
515
|
24 August 2023
|
|
Order & timings of works carried out & programme NEC4
|
|
7
|
565
|
20 August 2023
|
|
NEC3 Option B - BoQ Undermeasure
|
|
2
|
766
|
14 August 2023
|
|
New Webinar - FastDraft Masterclass: Compensation Events
|
|
13
|
821
|
18 September 2022
|
|
Can you say Scope will be completed during the defects period when it is not a defect?
|
|
5
|
643
|
1 August 2023
|
|
NEC4 Option B - Instruction Outside of our Scope
|
|
2
|
350
|
31 July 2023
|
|
NEC 4 - Option B Valuation of CE for correct discrepancy item
|
|
5
|
394
|
26 July 2023
|
|
NEC3 Programme Terminal Float
|
|
3
|
1141
|
24 July 2023
|
|
NEC4 Option B - Tender Vs Works Information
|
|
4
|
395
|
23 July 2023
|
|
Programme for Acceptance
|
|
2
|
651
|
23 July 2023
|
|
Can the client stand the contractor down for weather if weather risk is contractors responsibility
|
|
4
|
778
|
23 July 2023
|
|
NEC4 Opt C - Are Insurance Premium's part of the Contractor's PWDD or the Direct fee?
|
|
7
|
1490
|
4 July 2023
|
|
Ambiguity in Contractors Submission
|
|
1
|
277
|
3 July 2023
|
|
NEC Option C - Overtime
|
|
2
|
624
|
2 July 2023
|
|
Forecast costs in a CE - Forecast from when?
|
|
4
|
579
|
21 June 2023
|
|
NEC3 ECC3 Option A - Subcontractors prolongation costs allowable without any delay to Head Contract planned completion
|
|
4
|
751
|
19 June 2023
|
|
NEC 3 Option A - Accepted Contractors Design does not comply
|
|
4
|
1066
|
9 June 2023
|