# Why might the Employer add a KPI to the Incentive Schedule?

**URL:** <https://reachback.builtintelligence.com/t/why-might-the-employer-add-a-kpi-to-the-incentive-schedule/1028>\
**Category:** Secondary X, W and Y options\
**Created:** [14 November 2012 15:19 UTC](https://reachback.builtintelligence.com/t/why-might-the-employer-add-a-kpi-to-the-incentive-schedule/1028 "2012-11-14T15:19:09Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)\
**Post date:** [14 November 2012 15:19 UTC](https://reachback.builtintelligence.com/t/why-might-the-employer-add-a-kpi-to-the-incentive-schedule/1028/1 "2012-11-14T15:19:09Z")

</div>

Why might the Employer add a KPI to the Incentive Schedule?

---

<div class="post-metadata">

**Author:** ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)\
**Post date:** [14 November 2012 15:19 UTC](https://reachback.builtintelligence.com/t/why-might-the-employer-add-a-kpi-to-the-incentive-schedule/1028/2 "2012-11-14T15:19:22Z")

</div>

The Employer may add a Key Performance Indicator to the Incentive Schedule to encourage the Contractor to meet other objectives.