# Why might Sectional Completion be used?

**URL:** <https://reachback.builtintelligence.com/t/why-might-sectional-completion-be-used/893>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 13:35 UTC](https://reachback.builtintelligence.com/t/why-might-sectional-completion-be-used/893 "2012-10-16T13:35:46Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 13:35 UTC](https://reachback.builtintelligence.com/t/why-might-sectional-completion-be-used/893/1 "2012-10-16T13:35:46Z")

</div>

Why might Sectional Completion be used?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 13:35 UTC](https://reachback.builtintelligence.com/t/why-might-sectional-completion-be-used/893/2 "2012-10-16T13:35:58Z")

</div>

Sectional Completion is best used where the Employer wants the Contractor to complete a defined physical part of the works so that he or another contractor can take over that section entirely.