# Who is responsible for carrying out the tests?

**URL:** <https://reachback.builtintelligence.com/t/who-is-responsible-for-carrying-out-the-tests/590>\
**Category:** Testing and Defects\
**Created:** [14 October 2012 19:47 UTC](https://reachback.builtintelligence.com/t/who-is-responsible-for-carrying-out-the-tests/590 "2012-10-14T19:47:18Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:47 UTC](https://reachback.builtintelligence.com/t/who-is-responsible-for-carrying-out-the-tests/590/1 "2012-10-14T19:47:18Z")

</div>

Who is responsible for carrying out the tests?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:47 UTC](https://reachback.builtintelligence.com/t/who-is-responsible-for-carrying-out-the-tests/590/2 "2012-10-14T19:47:29Z")

</div>

Either the Contractor (including his Subcontractors and suppliers) or the Supervisor - the Works Information will specify which.