# Who choses the contract strategy for the project?

**URL:** <https://reachback.builtintelligence.com/t/who-choses-the-contract-strategy-for-the-project/647>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 13:24 UTC](https://reachback.builtintelligence.com/t/who-choses-the-contract-strategy-for-the-project/647 "2012-10-15T13:24:57Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 13:24 UTC](https://reachback.builtintelligence.com/t/who-choses-the-contract-strategy-for-the-project/647/1 "2012-10-15T13:24:57Z")

</div>

Who choses the contract strategy for the project?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 13:25 UTC](https://reachback.builtintelligence.com/t/who-choses-the-contract-strategy-for-the-project/647/2 "2012-10-15T13:25:08Z")

</div>

The Employer (advised by the Project Manager) chooses the contract strategy for the project.