# Who checks whether the Contractor’s work has reached the specified quality standards?

**URL:** <https://reachback.builtintelligence.com/t/who-checks-whether-the-contractor-s-work-has-reached-the-specified-quality-standards/572>\
**Category:** Testing and Defects\
**Created:** [14 October 2012 19:32 UTC](https://reachback.builtintelligence.com/t/who-checks-whether-the-contractor-s-work-has-reached-the-specified-quality-standards/572 "2012-10-14T19:32:16Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:32 UTC](https://reachback.builtintelligence.com/t/who-checks-whether-the-contractor-s-work-has-reached-the-specified-quality-standards/572/1 "2012-10-14T19:32:16Z")

</div>

Who checks whether the Contractor’s work has reached the specified quality standards?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:32 UTC](https://reachback.builtintelligence.com/t/who-checks-whether-the-contractor-s-work-has-reached-the-specified-quality-standards/572/2 "2012-10-14T19:32:29Z")

</div>

The Supervisor. Part of his role is to ensure, on behalf of the Employer, that the Contractor’s work is at the standards specified.