# Who carries the risk for damage to a section of the works that has been taken over by the Employer?

**URL:** <https://reachback.builtintelligence.com/t/who-carries-the-risk-for-damage-to-a-section-of-the-works-that-has-been-taken-over-by-the-employer/890>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 12:04 UTC](https://reachback.builtintelligence.com/t/who-carries-the-risk-for-damage-to-a-section-of-the-works-that-has-been-taken-over-by-the-employer/890 "2012-10-16T12:04:23Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 12:04 UTC](https://reachback.builtintelligence.com/t/who-carries-the-risk-for-damage-to-a-section-of-the-works-that-has-been-taken-over-by-the-employer/890/1 "2012-10-16T12:04:23Z")

</div>

Who carries the risk for loss, wear, or damage to a section of the works that has been taken over by the Employer?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 12:04 UTC](https://reachback.builtintelligence.com/t/who-carries-the-risk-for-damage-to-a-section-of-the-works-that-has-been-taken-over-by-the-employer/890/2 "2012-10-16T12:04:34Z")

</div>

The Employer assumes the risk for loss, wear, or damage to the section of works which he has taken over.