# Which Party provides the performance bond?

**URL:** <https://reachback.builtintelligence.com/t/which-party-provides-the-performance-bond/952>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 15:19 UTC](https://reachback.builtintelligence.com/t/which-party-provides-the-performance-bond/952 "2012-10-16T15:19:11Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 15:19 UTC](https://reachback.builtintelligence.com/t/which-party-provides-the-performance-bond/952/1 "2012-10-16T15:19:11Z")

</div>

Which Party provides the performance bond?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 15:19 UTC](https://reachback.builtintelligence.com/t/which-party-provides-the-performance-bond/952/2 "2012-10-16T15:19:35Z")

</div>

The Contractor gives the Employer a performance bond, provided by a bank or insurer which the Project Manager has accepted, for the amount stated in the Contract Data and in the form set out in the Works Information (see Clause X13.1).