# When should the Contractor remove Equipment from the Site?

**URL:** <https://reachback.builtintelligence.com/t/when-should-the-contractor-remove-equipment-from-the-site/633>\
**Category:** Title\
**Created:** [15 October 2012 12:24 UTC](https://reachback.builtintelligence.com/t/when-should-the-contractor-remove-equipment-from-the-site/633 "2012-10-15T12:24:40Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 12:24 UTC](https://reachback.builtintelligence.com/t/when-should-the-contractor-remove-equipment-from-the-site/633/1 "2012-10-15T12:24:40Z")

</div>

When should the Contractor remove Equipment from the Site?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 12:24 UTC](https://reachback.builtintelligence.com/t/when-should-the-contractor-remove-equipment-from-the-site/633/2 "2012-10-15T12:24:57Z")

</div>

When it is no longer needed. However, there are circumstances when the Project Manager allows it to be left in the works (see Clause 72.1).