# When should Option X7: Delay damages be included in the Contract?

**URL:** <https://reachback.builtintelligence.com/t/when-should-option-x7-delay-damages-be-included-in-the-contract/911>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 14:04 UTC](https://reachback.builtintelligence.com/t/when-should-option-x7-delay-damages-be-included-in-the-contract/911 "2012-10-16T14:04:52Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 14:04 UTC](https://reachback.builtintelligence.com/t/when-should-option-x7-delay-damages-be-included-in-the-contract/911/1 "2012-10-16T14:04:52Z")

</div>

When should Option X7: Delay damages be included in the Contract?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 14:05 UTC](https://reachback.builtintelligence.com/t/when-should-option-x7-delay-damages-be-included-in-the-contract/911/2 "2012-10-16T14:05:04Z")

</div>

It is recommended that Option X7 is included in most contracts.