# When does the Employer take over the works?

**URL:** <https://reachback.builtintelligence.com/t/when-does-the-employer-take-over-the-works/555>\
**Category:** Time\
**Created:** [14 October 2012 19:19 UTC](https://reachback.builtintelligence.com/t/when-does-the-employer-take-over-the-works/555 "2012-10-14T19:19:41Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:19 UTC](https://reachback.builtintelligence.com/t/when-does-the-employer-take-over-the-works/555/1 "2012-10-14T19:19:41Z")

</div>

When does the Employer take over the works?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:19 UTC](https://reachback.builtintelligence.com/t/when-does-the-employer-take-over-the-works/555/2 "2012-10-14T19:19:52Z")

</div>

The Employer takes over the works not later than two weeks after Completion (see Clause 35.1).