# When does the defects correction period begin?

**URL:** <https://reachback.builtintelligence.com/t/when-does-the-defects-correction-period-begin/613>\
**Category:** Testing and Defects\
**Created:** [15 October 2012 11:59 UTC](https://reachback.builtintelligence.com/t/when-does-the-defects-correction-period-begin/613 "2012-10-15T11:59:47Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 11:59 UTC](https://reachback.builtintelligence.com/t/when-does-the-defects-correction-period-begin/613/1 "2012-10-15T11:59:47Z")

</div>

When does the defects correction period begin?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 12:00 UTC](https://reachback.builtintelligence.com/t/when-does-the-defects-correction-period-begin/613/2 "2012-10-15T12:00:05Z")

</div>

For Defects that are notified before Completion, it begins at Completion. For other Defects, it begins when the Defect is notified (see Clause 43.2).