# When does loss of profit as a head of claim under the IFC form of contract constitute a valid claim?

**URL:** <https://reachback.builtintelligence.com/t/when-does-loss-of-profit-as-a-head-of-claim-under-the-ifc-form-of-contract-constitute-a-valid-claim/1542>\
**Category:** Contractor Claims\
**Created:** [18 January 2013 10:29 UTC](https://reachback.builtintelligence.com/t/when-does-loss-of-profit-as-a-head-of-claim-under-the-ifc-form-of-contract-constitute-a-valid-claim/1542 "2013-01-18T10:29:04Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 10:29 UTC](https://reachback.builtintelligence.com/t/when-does-loss-of-profit-as-a-head-of-claim-under-the-ifc-form-of-contract-constitute-a-valid-claim/1542/1 "2013-01-18T10:29:04Z")

</div>



---

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 10:29 UTC](https://reachback.builtintelligence.com/t/when-does-loss-of-profit-as-a-head-of-claim-under-the-ifc-form-of-contract-constitute-a-valid-claim/1542/2 "2013-01-18T10:29:26Z")

</div>

If the events led to a lower turnover which resulted in the loss of profit and further that it could be shown to have impacted upon the company’s overall profitability.