# When are parts of the works not defined within a section to be completed earlier than the whole works to be completed?

**URL:** <https://reachback.builtintelligence.com/t/when-are-parts-of-the-works-not-defined-within-a-section-to-be-completed-earlier-than-the-whole-works-to-be-completed/898>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 13:39 UTC](https://reachback.builtintelligence.com/t/when-are-parts-of-the-works-not-defined-within-a-section-to-be-completed-earlier-than-the-whole-works-to-be-completed/898 "2012-10-16T13:39:39Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 13:39 UTC](https://reachback.builtintelligence.com/t/when-are-parts-of-the-works-not-defined-within-a-section-to-be-completed-earlier-than-the-whole-works-to-be-completed/898/1 "2012-10-16T13:39:39Z")

</div>

When are parts of the works which are not defined within a section that is to be completed earlier than the whole works to be completed?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 13:39 UTC](https://reachback.builtintelligence.com/t/when-are-parts-of-the-works-not-defined-within-a-section-to-be-completed-earlier-than-the-whole-works-to-be-completed/898/2 "2012-10-16T13:39:50Z")

</div>

Any parts of the works that are not defined within a section are required to be complete when the whole works is complete.