# When are forecasts prepared?

**URL:** <https://reachback.builtintelligence.com/t/when-are-forecasts-prepared/744>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 15:36 UTC](https://reachback.builtintelligence.com/t/when-are-forecasts-prepared/744 "2012-10-15T15:36:59Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 15:36 UTC](https://reachback.builtintelligence.com/t/when-are-forecasts-prepared/744/1 "2012-10-15T15:36:59Z")

</div>

When are forecasts prepared?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 15:37 UTC](https://reachback.builtintelligence.com/t/when-are-forecasts-prepared/744/2 "2012-10-15T15:37:12Z")

</div>

Forecasts are prepared at the intervals stated in the Contract Data from the starting date until Completion of the whole of the works. An explanation of the changes made since the previous forecast is submitted with each forecast (see Clause 20.4).