# What should the Project Manager change when he has accepted a quotation for acceleration?

**URL:** <https://reachback.builtintelligence.com/t/what-should-the-project-manager-change-when-he-has-accepted-a-quotation-for-acceleration/747>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 16:44 UTC](https://reachback.builtintelligence.com/t/what-should-the-project-manager-change-when-he-has-accepted-a-quotation-for-acceleration/747 "2012-10-15T16:44:45Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 16:44 UTC](https://reachback.builtintelligence.com/t/what-should-the-project-manager-change-when-he-has-accepted-a-quotation-for-acceleration/747/1 "2012-10-15T16:44:45Z")

</div>

What should the Project Manager change when he has accepted a quotation for acceleration?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 16:44 UTC](https://reachback.builtintelligence.com/t/what-should-the-project-manager-change-when-he-has-accepted-a-quotation-for-acceleration/747/2 "2012-10-15T16:44:56Z")

</div>

When the Project Manager accepts a quotation for an acceleration, he changes the Prices, the Completion Date and the Key Dates accordingly and accepts the revised programme (see Clause 36.3).