# What should the Contractor show on each programme he submits for acceptance?

**URL:** <https://reachback.builtintelligence.com/t/what-should-the-contractor-show-on-each-programme-he-submits-for-acceptance/659>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 13:35 UTC](https://reachback.builtintelligence.com/t/what-should-the-contractor-show-on-each-programme-he-submits-for-acceptance/659 "2012-10-15T13:35:01Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 13:35 UTC](https://reachback.builtintelligence.com/t/what-should-the-contractor-show-on-each-programme-he-submits-for-acceptance/659/1 "2012-10-15T13:35:01Z")

</div>

What should the Contractor show on each programme he submits for acceptance?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 13:35 UTC](https://reachback.builtintelligence.com/t/what-should-the-contractor-show-on-each-programme-he-submits-for-acceptance/659/2 "2012-10-15T13:35:14Z")

</div>

On each programme he submits for acceptance, the Contractor should provide information which shows how each activity on the Activity Schedule relates to the operations (see Clause 31.4).