# What should a referral for adjudication contain?

**URL:** <https://reachback.builtintelligence.com/t/what-should-a-referral-for-adjudication-contain/1533>\
**Category:** Adjudication\
**Created:** [18 January 2013 10:22 UTC](https://reachback.builtintelligence.com/t/what-should-a-referral-for-adjudication-contain/1533 "2013-01-18T10:22:39Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 10:22 UTC](https://reachback.builtintelligence.com/t/what-should-a-referral-for-adjudication-contain/1533/1 "2013-01-18T10:22:39Z")

</div>



---

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 10:22 UTC](https://reachback.builtintelligence.com/t/what-should-a-referral-for-adjudication-contain/1533/2 "2013-01-18T10:22:51Z")

</div>

A referral should contain all of the arguments and evidence on which the referring party wishes to rely in support of its case.