# What must the Project Manager do before instructing the Contractor to submit a revised quotation for dealing with a compensation event?

**URL:** <https://reachback.builtintelligence.com/t/what-must-the-project-manager-do-before-instructing-the-contractor-to-submit-a-revised-quotation-for-dealing-with-a-compensation-event/112>\
**Category:** Compensation Events\
**Created:** [9 October 2012 20:12 UTC](https://reachback.builtintelligence.com/t/what-must-the-project-manager-do-before-instructing-the-contractor-to-submit-a-revised-quotation-for-dealing-with-a-compensation-event/112 "2012-10-09T20:12:28Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:12 UTC](https://reachback.builtintelligence.com/t/what-must-the-project-manager-do-before-instructing-the-contractor-to-submit-a-revised-quotation-for-dealing-with-a-compensation-event/112/1 "2012-10-09T20:12:28Z")

</div>

What must the Project Manager do before instructing the Contractor to submit a revised quotation for dealing with a compensation event?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:12 UTC](https://reachback.builtintelligence.com/t/what-must-the-project-manager-do-before-instructing-the-contractor-to-submit-a-revised-quotation-for-dealing-with-a-compensation-event/112/2 "2012-10-09T20:12:58Z")

</div>

Before instructing the Contractor to submit a revised quotation, the Project Manager must explain his reasons for doing so (see clause 62.4).