# What is the procedure if the Contractor’s quotation for reduced Prices or an earlier Completion Date is accepted?

**URL:** <https://reachback.builtintelligence.com/t/what-is-the-procedure-if-the-contractor-s-quotation-for-reduced-prices-or-an-earlier-completion-date-is-accepted/624>\
**Category:** Testing and Defects\
**Created:** [15 October 2012 12:10 UTC](https://reachback.builtintelligence.com/t/what-is-the-procedure-if-the-contractor-s-quotation-for-reduced-prices-or-an-earlier-completion-date-is-accepted/624 "2012-10-15T12:10:36Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 12:10 UTC](https://reachback.builtintelligence.com/t/what-is-the-procedure-if-the-contractor-s-quotation-for-reduced-prices-or-an-earlier-completion-date-is-accepted/624/1 "2012-10-15T12:10:36Z")

</div>

What is the procedure if the Contractor’s quotation for reduced Prices or an earlier Completion Date is accepted?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 12:10 UTC](https://reachback.builtintelligence.com/t/what-is-the-procedure-if-the-contractor-s-quotation-for-reduced-prices-or-an-earlier-completion-date-is-accepted/624/2 "2012-10-15T12:10:47Z")

</div>

The Works Information, the Prices and the Completion Date will be changed accordingly. This change is not a compensation event.