# What is the procedure for tests and inspection?

**URL:** <https://reachback.builtintelligence.com/t/what-is-the-procedure-for-tests-and-inspection/567>\
**Category:** Testing and Defects\
**Created:** [14 October 2012 19:28 UTC](https://reachback.builtintelligence.com/t/what-is-the-procedure-for-tests-and-inspection/567 "2012-10-14T19:28:48Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:28 UTC](https://reachback.builtintelligence.com/t/what-is-the-procedure-for-tests-and-inspection/567/1 "2012-10-14T19:28:48Z")

</div>

What is the procedure for tests and inspection?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:29 UTC](https://reachback.builtintelligence.com/t/what-is-the-procedure-for-tests-and-inspection/567/2 "2012-10-14T19:29:04Z")

</div>

The Supervisor and Contractor notify each other before their respective tests start and, when the tests has been completed, they notify each other of the results (see Clause 40.3).