# What is the Price for Work Done to Date comprised of?

**URL:** <https://reachback.builtintelligence.com/t/what-is-the-price-for-work-done-to-date-comprised-of/655>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 13:31 UTC](https://reachback.builtintelligence.com/t/what-is-the-price-for-work-done-to-date-comprised-of/655 "2012-10-15T13:31:59Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 13:31 UTC](https://reachback.builtintelligence.com/t/what-is-the-price-for-work-done-to-date-comprised-of/655/1 "2012-10-15T13:31:59Z")

</div>

What is the Price for Work Done to Date comprised of?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 13:32 UTC](https://reachback.builtintelligence.com/t/what-is-the-price-for-work-done-to-date-comprised-of/655/2 "2012-10-15T13:32:14Z")

</div>

The Price for Work Done to Date is the total of the Prices for each group of completed activities and each completed activity which is not in a group (see Clause 11.2(27)).