# What is the Price Adjustment Factor?

**URL:** <https://reachback.builtintelligence.com/t/what-is-the-price-adjustment-factor/855>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 11:25 UTC](https://reachback.builtintelligence.com/t/what-is-the-price-adjustment-factor/855 "2012-10-16T11:25:43Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 11:25 UTC](https://reachback.builtintelligence.com/t/what-is-the-price-adjustment-factor/855/1 "2012-10-16T11:25:43Z")

</div>

What is the Price Adjustment Factor?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 11:25 UTC](https://reachback.builtintelligence.com/t/what-is-the-price-adjustment-factor/855/2 "2012-10-16T11:25:55Z")

</div>

The Price Adjustment Factor is the total of the products of each of the proportions stated in the Contract Data multiplied by (L-B)/B for the index linked to it (see Clause X1.1©).