# What is Disallowed Cost?

**URL:** <https://reachback.builtintelligence.com/t/what-is-disallowed-cost/699>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 15:01 UTC](https://reachback.builtintelligence.com/t/what-is-disallowed-cost/699 "2012-10-15T15:01:19Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 15:01 UTC](https://reachback.builtintelligence.com/t/what-is-disallowed-cost/699/1 "2012-10-15T15:01:19Z")

</div>

What is Disallowed Cost?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 15:01 UTC](https://reachback.builtintelligence.com/t/what-is-disallowed-cost/699/2 "2012-10-15T15:01:32Z")

</div>

Disallowed Cost is cost which the Project Manager decides:

```
	Is not justified by the Contractor’s accounts and records,

	Should not have been paid to a Subcontractor in accordance with his contract,

	Was incurred only because the Contractor did not: give an early warning; or follow an acceptance or procurement procedure stated in the Works Information (see Clause 11.2(25)).
```