# What is Completion?

**URL:** <https://reachback.builtintelligence.com/t/what-is-completion/1121>\
**Category:** General\
**Created:** [20 November 2012 14:24 UTC](https://reachback.builtintelligence.com/t/what-is-completion/1121 "2012-11-20T14:24:14Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)\
**Post date:** [20 November 2012 14:24 UTC](https://reachback.builtintelligence.com/t/what-is-completion/1121/1 "2012-11-20T14:24:14Z")

</div>

What is completion?

---

<div class="post-metadata">

**Author:** ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)\
**Post date:** [20 November 2012 14:26 UTC](https://reachback.builtintelligence.com/t/what-is-completion/1121/2 "2012-11-20T14:26:25Z")

</div>

Clause 11.2(2) defines Completion as ‘when the Contractor has done all the work which the Works Information states he is to do by the completion date and corrected notified Defects which would have prevented use of the works by the Employer and Others.’