# What if the job is not notifiable and there is no principal contractor?

**URL:** <https://reachback.builtintelligence.com/t/what-if-the-job-is-not-notifiable-and-there-is-no-principal-contractor/1344>\
**Category:** CDM\
**Created:** [13 January 2013 10:07 UTC](https://reachback.builtintelligence.com/t/what-if-the-job-is-not-notifiable-and-there-is-no-principal-contractor/1344 "2013-01-13T10:07:27Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [13 January 2013 10:07 UTC](https://reachback.builtintelligence.com/t/what-if-the-job-is-not-notifiable-and-there-is-no-principal-contractor/1344/1 "2013-01-13T10:07:27Z")

</div>



---

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [24 January 2013 13:21 UTC](https://reachback.builtintelligence.com/t/what-if-the-job-is-not-notifiable-and-there-is-no-principal-contractor/1344/2 "2013-01-24T13:21:12Z")

</div>

The contractor will be required to:

```
	inform the client of their CDM 2007 duties if this has not already been done

	plan, manage and monitor the construction work to make sure it is carried out without risks to health and safety

	provide information, training and a suitable site induction for their workforce

	make sure the site is suitably fenced and prevent access by unauthorised persons

	ensure adequate welfare facilities for those working on the site
```