# What happens if TRA (Time Risk Allowance) is not needed by the Contractor?

**URL:** <https://reachback.builtintelligence.com/t/what-happens-if-tra-time-risk-allowance-is-not-needed-by-the-contractor/1050>\
**Category:** Risk and Insurance\
**Created:** [15 November 2012 13:53 UTC](https://reachback.builtintelligence.com/t/what-happens-if-tra-time-risk-allowance-is-not-needed-by-the-contractor/1050 "2012-11-15T13:53:08Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)\
**Post date:** [15 November 2012 13:53 UTC](https://reachback.builtintelligence.com/t/what-happens-if-tra-time-risk-allowance-is-not-needed-by-the-contractor/1050/1 "2012-11-15T13:53:08Z")

</div>

What happens if TRA (Time Risk Allowance) is not needed by the Contractor?

---

<div class="post-metadata">

**Author:** ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)\
**Post date:** [15 November 2012 13:55 UTC](https://reachback.builtintelligence.com/t/what-happens-if-tra-time-risk-allowance-is-not-needed-by-the-contractor/1050/2 "2012-11-15T13:55:12Z")

</div>

It will be converted to total float for non-critical activities and will bring forward planned Completion for the critical path items creating terminal float.