# What happens if the Project Manager has instructed the Contractor to stop working, because of a fault of the Employer, and has not instructed to re-start work?

**URL:** <https://reachback.builtintelligence.com/t/what-happens-if-the-project-manager-has-instructed-the-contractor-to-stop-working-because-of-a-fault-of-the-employer-and-has-not-instructed-to-re-start-work/548>\
**Category:** Time\
**Created:** [14 October 2012 19:11 UTC](https://reachback.builtintelligence.com/t/what-happens-if-the-project-manager-has-instructed-the-contractor-to-stop-working-because-of-a-fault-of-the-employer-and-has-not-instructed-to-re-start-work/548 "2012-10-14T19:11:47Z")\
**Posts on this page:** 1\
**Showing post:** 2

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:12 UTC](https://reachback.builtintelligence.com/t/what-happens-if-the-project-manager-has-instructed-the-contractor-to-stop-working-because-of-a-fault-of-the-employer-and-has-not-instructed-to-re-start-work/548/2 "2012-10-14T19:12:00Z")

</div>

If the Project Manager has instructed the Contractor to stop or not start working because of a fault of the Employer and has not instructed the Contractor to re-start work within thirteen weeks, then the Contractor is entitled to terminate the contract (see Clause 91.6 R19).

---