# What happens if the Project Manager does not assess a compensation event within the time allowed?

**URL:** <https://reachback.builtintelligence.com/t/what-happens-if-the-project-manager-does-not-assess-a-compensation-event-within-the-time-allowed/135>\
**Category:** Compensation Events\
**Created:** [9 October 2012 20:42 UTC](https://reachback.builtintelligence.com/t/what-happens-if-the-project-manager-does-not-assess-a-compensation-event-within-the-time-allowed/135 "2012-10-09T20:42:10Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:42 UTC](https://reachback.builtintelligence.com/t/what-happens-if-the-project-manager-does-not-assess-a-compensation-event-within-the-time-allowed/135/1 "2012-10-09T20:42:10Z")

</div>

What happens if the Project Manager does not assess a compensation event within the time allowed?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:42 UTC](https://reachback.builtintelligence.com/t/what-happens-if-the-project-manager-does-not-assess-a-compensation-event-within-the-time-allowed/135/2 "2012-10-09T20:42:31Z")

</div>

If the Project Manager does not assess a compensation event within the time allowed, the Contractor may notify the Project Manager to this effect (see Clause 64.4).