# What happens if the Completion Date is changed to a later date after delay damages have been paid?

**URL:** <https://reachback.builtintelligence.com/t/what-happens-if-the-completion-date-is-changed-to-a-later-date-after-delay-damages-have-been-paid/908>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 14:02 UTC](https://reachback.builtintelligence.com/t/what-happens-if-the-completion-date-is-changed-to-a-later-date-after-delay-damages-have-been-paid/908 "2012-10-16T14:02:54Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 14:02 UTC](https://reachback.builtintelligence.com/t/what-happens-if-the-completion-date-is-changed-to-a-later-date-after-delay-damages-have-been-paid/908/1 "2012-10-16T14:02:54Z")

</div>

What happens if the Completion Date is changed to a later date after delay damages have been paid?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 14:03 UTC](https://reachback.builtintelligence.com/t/what-happens-if-the-completion-date-is-changed-to-a-later-date-after-delay-damages-have-been-paid/908/2 "2012-10-16T14:03:05Z")

</div>

If the Completion Date is changed to a later date after delay damages have been paid, the Employer repays the overpayment of damages (see Clause X7.2).