# What does the Project Manager do once he has accepted a quotation for an acceleration?

**URL:** https://reachback.builtintelligence.com/t/what-does-the-project-manager-do-once-he-has-accepted-a-quotation-for-an-acceleration/710
**Category:** NEC3 and NEC4 Contracts
**Created:** [15 October 2012 15:09 UTC](https://reachback.builtintelligence.com/t/what-does-the-project-manager-do-once-he-has-accepted-a-quotation-for-an-acceleration/710 "2012-10-15T15:09:03Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 15:09 UTC](https://reachback.builtintelligence.com/t/what-does-the-project-manager-do-once-he-has-accepted-a-quotation-for-an-acceleration/710/1 "2012-10-15T15:09:03Z")

</div>

What does the Project Manager do once he has accepted a quotation for an acceleration?

---

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 15:09 UTC](https://reachback.builtintelligence.com/t/what-does-the-project-manager-do-once-he-has-accepted-a-quotation-for-an-acceleration/710/2 "2012-10-15T15:09:14Z")

</div>

When the Project Manager has accepted a quotation for an acceleration, he changes the Prices, the Completion Date and the Key Dates accordingly and accepts the revised programme (see Clause 36.3).